Tales from the National Appeal Chamber: Requiring additional evidence is an unreasonable barrier to fee indexation
The last two years in the public procurement market have been stormy. The Covid-19 pandemic and the war in Ukraine have caused a steady and dynamic increase in the prices of materials and services, and disrupted supply chains, translating into record inflation rates and unprecedented fee increases. With this tough economic situation directly affecting the market, contractors have faced the difficult task of indexing their fees in public contracts. The National Appeal Chamber, which hears challenges in public procurement matters in Poland, gave essential guidance on this issue in its ruling of 28 November 2023 (case no. KIO 3389/23).
Tales from the National Appeal Chamber: Amounts for basic and optional procurement should be clearly defined
Sometimes, before opening the bids, the contracting authority already knows the amount it will allocate for both the basic contract and the optional contract. How should it indicate these amounts for finalising the procedure? When can the procedure be cancelled under Art. 255(3) of the Public Procurement Law if the contract provides for the right of an option? In a recent ruling, the National Appeal Chamber answered these and other questions.
Tales from the National Appeal Chamber: Trade secrets must be proven
Public procurement is subject to the general principle of openness. Sometimes, this conflicts with the interests of contractors, who can protect their companies’ valuable information and knowhow by designating it as a trade secret. But this is not an automatic process, as it requires contractors to make a credible showing of the rationale for protecting the information. In a recent ruling, the National Appeal Chamber clarified the conditions for correctly reserving trade secrets.
Can penalties in public procurement exceed the contract price?
The Polish Public Procurement Law does not specify an upper limit for contractual penalties. However, if the penalties are out of line with the realities of the contract, the contractor can seek review by the National Appeal Chamber. In a recent ruling, the chamber cut the penalties to 30% of the contractor’s gross fee.
Tales from the National Appeal Chamber: Validity of bid bond vs. bid validity period
As the host of the procedure, in the contract documentation the contracting authority should specify the formal and technical requirements for a bid bond. In some procurement procedures, the contracting authority requires contractors to submit a bid bond with a validity extending beyond the bid validity period. In a recently issued ruling, the National Appeal Chamber opined on whether such provisions of the terms of reference are permissible, or are invalid by virtue of law (case no. KIO 3482/21).
Tales from the National Appeal Chamber: How to explain a bid price when requested by the contracting authority?
A contractor is obliged to calculate the bid price fairly and factor in everything that follows from the terms of reference, including typical risks associated with contract performance, so that the bid is realistic and allows for proper performance of the contract. If the bid price appears abnormally low or is otherwise questionable, the contractor must explain it in detail.
Tales from the National Appeal Chamber: A contest entry inconsistent with the Public Procurement Law or the contest rules will not be considered
The purpose for stating the projected execution costs in the rules for a contest is for contestants to be aware of the contracting authority’s financial capabilities. Contestants should take this value into account when preparing their entries, or their entry will not be considered by the contest jury, the National Appeal Chamber held in its ruling of 10 January 2022 (KIO 3624/21).
Tales from the National Appeal Chamber: Grave professional misconduct must be caused by the contractor
When filling in the European Single Procurement Document (ESPD) form, contractors must answer the question whether they have committed grave professional misconduct while performing previous contracts. This question is closely correlated with the condition for exclusion under Art. 109(1)(5) of the Public Procurement Law, which specifies that this concerns violations that are serious and self-caused. Therefore, a contractor does not necessarily have to mention any and all delays or complications that occurred during the performance of previous contracts. In this context, an interesting ruling was issued by the National Appeal Chamber on 4 June 2021 (KIO 1087/21) indicating how this question from the ESPD form should be interpreted.
Tales from the National Appeal Chamber: Can a discrepancy in a bid price between figures and words be treated as a typographical error?
Sometimes typos occur when preparing bid documents, and can be corrected by the contracting authority if the contractor provides the required clarification. But not all mistakes can be cured, especially those concerning the bid price, as they directly affect the contractor’s position in the ranking. An example of such a mistake is when a price is given in figures and then restated differently in words. The National Appeal Chamber explained in its ruling of 1 June 2021 (case no. KIO 1040/21) why such a mistake cannot be corrected.
Tales from the National Appeal Chamber: When can a performance bond exceed 5% of the total bid price or the value of the contracting authority’s liability?
When preparing contract documents, the contracting authority must decide the amount of the performance bond it will demand. As a rule, this security should amount to 5% of the total bid price or the value of the contracting authority’s liability. But when can this threshold be exceeded, and to what maximum value? This and other questions were answered in the ruling of the National Appeal Chamber of 21 October 2020 (KIO 1381/20).
Tales from the National Appeal Chamber: Change in the composition of a consortium during competitive dialogue
A two-stage competitive dialogue often extends the procurement procedure to many months. During that time, as a result of various circumstances, changes in the parties to a consortium may occur, often beyond the contractors’ control. In this situation, will the remaining contractors still be entitled to submit a bid, or should they be excluded from the procedure? In its ruling of 22 January 2021 (case no. KIO 3357/20), the National Appeal Chamber held that to avoid negative consequences for contractors, two key conditions must be met.
Tales from the National Appeal Chamber: The specialised nature of medical procurements justifies tougher conditions for participating in tenders
When establishing the conditions for participating in a contract award procedure, contracting authorities often face the dilemma of how to reflect the specific subject matter of the procurement without infringing the principle of proportionality. This task is even harder when the procurement involves specialised medical equipment, where improper servicing could put patients’ life or health at risk. Do such circumstances justify limiting the number of bidders seeking a contract? Yes, the National Appeal Chamber held in its ruling of 29 January 2021 (case no. KIO 3489/20).